California’s Title 24 energy code, formally Part 6 of the California Building Standards Code, sets minimum energy efficiency rules for new commercial buildings, additions and many alterations, including lighting, HVAC, envelope and, for some new buildings, solar and battery storage. For a San Diego project it shapes design choices, adds required documents and tests, and has to be shown on plans before the city or county will issue a permit.
What Title 24 Part 6 covers
The Building Energy Efficiency Standards are written by the California Energy Commission and updated on a three-year cycle. The 2025 standards took effect on January 1, 2026, and the version that applies to your project depends on when the permit application is submitted. Ask your designer which edition your project falls under.
For nonresidential buildings, the code covers:
- Envelope: insulation, windows, skylights and roofing, including cool roof requirements in some cases.
- Mechanical: HVAC efficiency, controls, economizers, duct sealing and ventilation.
- Lighting: lighting power limits and required controls such as occupancy sensing, daylighting and automatic shutoff.
- Water heating: equipment efficiency and distribution.
- Electrical: metering, demand response readiness and other provisions.
- Solar and storage: recent editions added solar PV and battery storage requirements for many new nonresidential building types.
Recent cycles have also pushed new construction toward heat pumps for space and water heating. Our guide on all-electric buildings in San Diego covers what that means on site.
What triggers it on a commercial project
New buildings and additions must comply. Alterations are where many owners get surprised. Replacing a large share of a space’s lighting, changing out HVAC equipment, adding ducts or replacing a roof can each trigger requirements for the parts you touch. A tenant improvement that rewires lighting will usually need controls that meet the current code, even if the old lighting had none.
Plan for this in the budget. A lighting upgrade that looked like a fixture swap can grow to include sensors, dimming and testing. That cost usually pays back through lower bills, but it should be in the bid, not a change order.
Common alteration triggers to check early:
- Replacing or rewiring a significant share of the lighting in a space.
- Replacing rooftop HVAC units or adding new mechanical systems.
- Extending or replacing ductwork.
- Replacing a large area of roofing, which can bring cool roof and insulation rules into play.
- Adding conditioned space, such as enclosing a warehouse area for offices.
San Diego climate zones
Title 24 uses climate zones, and San Diego County spans several. Coastal areas fall in a mild marine zone, inland valleys in a warmer zone, the mountains in a colder zone and the desert east of the mountains in a hot zone. Requirements for envelope, HVAC and cool roofs can differ between them, so a design that works in La Jolla may need changes for El Cajon or Ramona. Confirm the climate zone from the project’s location before design starts.
Compliance paths and documents
There are two main ways to show compliance.
- Prescriptive: meet each listed requirement as written. Simpler for small projects and alterations.
- Performance: model the whole building with approved software and show it uses no more energy than a code-compliant baseline. More flexible, and common for new buildings.
Either way, the project needs Title 24 compliance documents. For nonresidential work these include certificates of compliance submitted with plans, certificates of installation completed by the contractor, and certificates of acceptance after testing. The building department checks them at plan review and before final inspection.
Acceptance testing
Nonresidential projects require acceptance tests for many lighting controls and mechanical systems. These confirm that sensors, economizers, controls and other equipment actually work as designed. Certified acceptance test technicians perform many of these tests. Schedule them early, since failed tests can delay final inspection, and the fix is often a control setting or a sensor location that would have been easy to catch during installation.
- Identify which acceptance tests apply during design.
- Book a certified technician before installation is complete.
- Have the installer on site for testing to fix issues the same day.
- Collect completed certificates of acceptance for the inspector.
- Hand the owner a record of control settings so they don’t get overridden later.
What this means for your bid and your building
For contractors, Title 24 knowledge is a selling point. Owners want a bid that includes code-required controls and testing up front, and they remember who surprised them with change orders. For owners, a code-compliant building is usually cheaper to run. Check with SDG&E about new construction or efficiency programs that may help with design or equipment costs, and confirm current program terms before you count on them. Code requirements and program rules change, so confirm details with the California Energy Commission and your local building department.
How the chamber helps
The San Diego Green Chamber connects owners with green building and construction firms that work with Title 24 every day, and gives contractors a network of peers who share what plan checkers are flagging. Every member commits to reducing energy and water use, and the chamber offers education, resources and a unified voice on policy that affects how San Diego builds. See what membership includes.
Questions
What is Title 24 Part 6?
It is California’s Building Energy Efficiency Standards, written by the California Energy Commission. It sets minimum energy rules for new buildings, additions and many alterations.
Does Title 24 apply to tenant improvements?
Often, yes. Altering lighting, HVAC, ducts or the roof can trigger requirements for the parts of the building you change.
What is an acceptance test?
A required test on nonresidential projects that confirms lighting controls and mechanical systems work as designed. Many are performed by certified acceptance test technicians.
Which Title 24 edition applies to my project?
Generally the one in effect when the permit application is submitted. The 2025 standards took effect January 1, 2026. Confirm with your designer and building department.